Remedial Actions Implemented to Date

Significant progress has been made in implementing the cleanup remedies at the Livermore Site to include:

  • Operating 30 ground water and 5 soil vapor treatment facilities
  • Conducting two Five-year Reviews where the remedies were determined to be effective
  • Conducting four soil removals
  • Receiving State of California closure on Treatment Facility F vadose zone cleanup
  • Preparing four Explanation of Significant Differences
  • Treating over 2 billion gallons of ground water
  • Removing over 1,600 kg of VOCs from the subsurface



Next: Future Work